A communications test is used to check whether the alarm panel is communicating properly.
If Comm Test is not finished, it will continue to run even if you exit program mode.

To perform a local communications test (not logged by central station):
  1. Enter the Status & Settings menu.
  2. Scroll until System Tests is listed, Press Enter.
  3. Enter your master code and press OK.
  4. Press Comm Test.
The panel displays if the comm test was successful or not.


To perform a communications test with the central station:
  1. Call the central station (1-800-268-6870) or Reed Security support (306-653-3200 option 3) and tell the operator that you will be testing the system.
  2. Arm the system.
  3. Test an emergency panic icon and trip at least one sensor of each type (fire, intrusion, etc.) to verify that the appropriate alarms are working correctly. There could be a 30 second delay on intrusion devices.
  4. When you finish testing the system, call the central station or Reed Security to verify that the alarms were received.
If your system is not connected to a central monitoring station you won’t be able to perform the communication test. 


    • Related Articles

    • DSC Maxsys - System/Communications Test

      This option will test the system. This bell/siren will activate for two seconds and system will send a test code transmission to the monitoring station. To start the System test, perform the following: Press [*] [6], then enter a valid access code ...
    • DSC Alexor - System Test

      Here are step-by-step instructions on how to perform a system/communications test of your alarm system (DSC Alexor) Security Alarm Monitoring System, and how to silence that beep: Call Reed Security Support (306-653-3200 option 3) or your Monitoring ...
    • DSC - Communications Failure Troubleshooting

      If your DSC alarm system is not communicating with the monitoring station, this is often due to some issue with the communications line (landline or cellular communicator). Often repair work or services changes have been made to the landline which ...
    • Simon XT - Communications Test

      Test communications between your system and the central monitoring station at least once a week to make sure you have the proper telephone connection. To test communications with the monitoring station with your system, follow the instructions below: ...
    • Simon XTi - Set Time

      Setting Time for a Simon XTi Panel Tap on the gear in lower corner of the screen. Tap on the down arrow to the last page. Tap the Enter button next to the top option labeled "Set Date/Time" Enter you four(4) digit MASTER CODE, tap OK button To make ...